S.No District Name Works Sanctioned Works Completed Works In Progress Works not Started
1 Mulugu 4 0 1 3
TOTAL 4 0 1 3








S.No Project Id Project Name Agreement Date Completion Date as per Agreement Tech Sanction Amount Value of work done Stage of Work
1 1 Test Project 01/01/1970 01/01/1970 200 Work in Progress
2 2 Test Project 01/01/1970 01/01/1970 200 Not Started
3 26 Construction of 50 bedded Critical Care Block at DH Mulugu 21/09/2023 20/09/2024 23,75,00,000 Not Started
4 32 Upgradtion of DH Mulugu 21/06/2022 20/04/2023 52,13,00,000 Not Started